Eggners Ferry Bridge Repair Information
Posted: 31-Aug-2012 3:29AM CDT

The Eggners Ferry Bridge was reopened as planned by Memorial Day this year. This information is posted here for historical purposes. From Kentucky Transportation Cabinet Department of Highways District 1 (May 18, 2012):

Repairs on track for Eggners Ferry Bridge to reopen by Memorial Day weekend
Concrete pour on deck section tentatively scheduled for Sunday

AURORA, Ky.– Repairs to the U.S. 68/KY 80 Eggners Ferry Bridge are on track for reopening of the damaged bridge in time for the Memorial Day weekend. 

Crews from Hall Contracting of Kentucky Inc. lifted a new truss span into place on Tuesday, May 15. Today, they are placing the last of the reinforcing steel and forms required for pouring a concrete deck on the new span this weekend.  They plan complete final preparations on Saturday morning to be prepared to pour concrete starting on Sunday morning.  The concrete pour is expected to take about 5 to 6 hours to complete.

 

 

Due to the amount of truck traffic the concrete work will generate, barricades will be up at each end of the bridge and access will be restricted.  On the Marshall County side no one will be able to get any closer than barricades at the US 68/KY 80 intersection.  However, the public will be able to watch the work from Ken Lake State Resort Park.  Restricting access to the bridge to essential personnel only will allow the concrete trucks plenty of room to maneuver safely. 

The Eggners Ferry Bridge crosses Kentucky Lake between Marshall and Trigg counties.  A 322-foot span of the bridge was destroyed when struck by an 8200 ton cargo ship on the night of Jan. 26.  The Kentucky Transportation Cabinet (KYTC) awarded an emergency contract for the repair project to Hall Contracting. The contract specifies a deadline of Sunday, May 27, for completion of repairs and reopening the bridge to traffic.

KYTC District 1 Chief Engineer Jim LeFevre said security will be stepped up around the bridge this weekend to maintain safety at the site.  While recognizing there is a lot of public interest in the work, LeFevre asked that everyone stay off the bridge and its approaches to help speed the work and avoid creating safety hazards.

“Truck access to the bridge and approaches is critical for this phase of the bridge repair operation,” LeFevre said.  “Cement trucks will be turning around on the bridge approach causeway and backing up along the bridge approach as they go about making deliveries.  To assure the safety of both workers and the public – and timely completion of the required work – we are asking area law enforcement agencies to write trespassing citations to anyone who goes beyond our ‘Road Closed’ signs at each end of the bridge work zone.”

“The amount of concrete required for the new deck also means there will be a number of trucks traveling along KY 80 between the concrete mixing plant in Murray and the bridge,” LeFevre added.  “We’re urging everyone to use caution along this route due to the increase in truck traffic.”

LeFevre said any number of additional issues could hinder progress on the bridge, including the weather.  However, he said he is optimistic that traffic can be fully restored by the Memorial Day deadline.

After the 8,200-ton Delta Mariner knocked out the span, electrical power to the structure – originally fed from Trigg County on the eastern side – had to be temporarily rerouted to be supplied from Marshall County.  A KYTC electrical crew is continuing work along the bridge to restore the power supply from the east end.

Once a new deck is poured, KYTC construction inspectors will check the concrete to ensure it is of proper strength.  In addition, KYTC bridge inspectors will check and document the new span.  KYTC inspectors expect to complete required safety checks within a few hours.

The bridge serves as the western entrance to The Land Between The Lakes National Recreation Area.  In addition to providing a key transportation link for area commuters, the bridge is a connecting point for tourism in Kentucky’s 15-county Western Lakes Region. 

According to Kentucky’s Western Waterland, a regional tourism promotion group, tourism dollars provide a direct annual contribution of $472 million to the region and a direct contribution of $7.4 billion to the Kentucky economy statewide.

Video and photos of continuing work on the bridge deck are posted atwww.facebook.com/kytcdistrict1.  You do not have to be a Facebook member to access this

 

Comments: [No Comments] -- [View/Post Comments]
[URL for This Item]

[View all Topics] [View all News Items]

Comments

Updated: 31-Aug-2012 3:29AM CDT

Note: This website makes heavy use of the CSS standard. Your browser appears not to support CSS, or you may have CSS turned off for some odd reason. This page may render incorrectly since you are not using CSS. (more information on CSS)

Featured Items: [About this Site] [Hal Rogers Parkway] [Clay's Ferry Bridge] [Glen Lily Road Overpass] [Suggested Links] [Travel Information] [William H. Natcher Bridge]

Copyright © 2001-2023 by Jeffrey Carlyle. All rights reserved. This website is not associated with any government agency.