KY 32 Roadway Improvement Project Update in Rowan County
From Kentucky Transportation Cabinet District 9:
KY 32 Roadway Improvement Project Update in Rowan County.
KY-32 from Viking Drive North to Hickory Point
FLEMINGSBURG, Ky. (Nov.18, 2026)– The Kentucky Transportation Cabinet, (KYTC) announces upcoming phases of work on KY 32 roadway improvement project update in Rowan County. This project is anticipated to take approximately three years to complete.
Phases of Work
Several utilities are impacted by the roadway project, and some relocation work has already been completed
Rowan Water, Morehead Utility Plant Board Sewer, and Morehead Utility Plant Board Gas relocations are being performed under the roadway construction contract. All other utility relocations have been or are being completed by the respective utility providers or contractors hired directly by those providers.
If you experience a utility service issue or have questions regarding your utility service, please contact your utility provider directly.
- Utility Relocations:
- Tennessee Gas Pipeline: Relocation work has been recently completed.
- Overhead Utilities: Relocation activities will continue over the next three to four months.
- Water, Sewer, and Gas Distribution: Relocation work will continue throughout the duration of the roadway project.
Roadway Construction Activities Planned into Spring 2027
Construction will continue on the Pennington Flats Road Bridge over Big Brushy Creek.
Excavation activities will also begin in the area between Copperas Hollow Road and Limestone Road. Excavated material will be transported using articulated off-road trucks. These trucks will cross KY-32 and Big Brushy Creek using a temporary creek crossing before depositing the material at the former auto salvage yard. The majority of the earthwork completed to date is classified as clearing and grubbing, not Excavation.
The contractor may utilize blasting to complete portions of the excavation work. If utilized, blasting operations could result in temporary traffic delays of up to approximately 15 to 20 minutes.
Road work schedules may be adjusted if inclement weather or other unforeseen delays occur. Motorists are asked to heed all warning signs, slow down in work zones and remain aware of workers and construction equipment when traveling.
The KY-32 Roadway Improvement Project in Rowan County has been awarded to Walker Construction of Mt. Sterling, Kentucky.
Visit GoKY.ky.govonline for Kentucky travel and traffic information, or use the Waze mobile application. Follow Transportation Cabinet operations in northeast Kentucky on social media @KYTCDistrict 9.