I-71 Widening in Carroll and Gallatin Counties: Final Paving Complete, Completion Expected Dec. 1: District 6 ROADSHOW for the Week of Nov. 22, 2026

Final surface paving is complete in both directions on the Interstate 71 widening in Carroll County and Gallatin County, District 6’s Roadshow for the week of Nov. 22 reports. The project takes the interstate from two lanes in each direction to three between mile points 52.77 and 57.36, and it is now expected to be completed Dec. 1, 2026, weather permitting; earlier this month the expected completion was still November. Intermittent lane closures will still be needed while crews finish shoulder work and other remaining tasks.

Next door, a separate pavement rehabilitation project on I-71 between Sparta Pike (KY 35) and northeast of the Boone Road (KY 465) overpass (mile points 56.64 to 59.94) is nearly done, also with a Dec. 1 completion date. In Campbell County, the Reduced Conflict U-Turn at US 27 and Kenton Station Road (KY 1936) partially opened Nov. 16. No major work is planned over the Thanksgiving weekend, Nov. 26 to 29.

Earlier: I-71 Widening in Carroll and Gallatin Counties Nears Completion: Single Lane Closure on I-71 Southbound on Friday, Nov. 13; Final Paving Begins on the I-71 Widening in Carroll and Gallatin Counties: District 6 ROADSHOW for the Week of Oct. 25, 2026

The full Roadshow from Kentucky Transportation Cabinet District 6:

ROADSHOW
Week of Nov. 22, 2026
Here, you'll find all of the NEW projects, maintenance, and other work taking place in our 11 county district:
Boone, Bracken, Campbell, Carroll, Gallatin, Grant, Harrison, Kenton, Owen, Pendleton, and Robertson Counties
Click the button below to take a look at all of the projects happening right now.
CLICK HERE: Full ROADSHOW Report [Outside Link]
New items or changes in project status are italicized.
*Inclement weather or other unforeseen circumstances may occur, so the information below is strictly of an advisory nature and is subject to change with no notice.
Pothole patching, sweeping, drain & ditch work, litter pick up, brush clearing, culvert repairs and additional work by our KYTC maintenance crews may occur on major interstates/state routes during non-peak daytime hours and at night.
Motorists should watch for roadside maintenance on interstates/highways throughout the district DAILY. We will send out information to the public if these tasks require significant impacts to traffic.
Looking for information regarding the Brent Spence Bridge Corridor Project? Please visit the project website [Outside Link] for traffic impacts and more information regarding the work. You can also sign up for email and text alerts here [Outside Link].
No major work is expected to take place over the Thanksgiving Holiday Weekend (Thursday, Nov. 26 through Sunday, Nov. 29)
BOONE, CAMPBELL AND KENTON COUNTIES
A bridge maintenance project to improve conditions on interstate bridges in Boone, Kenton and Campbell counties is in progress.
On Thursday, Nov. 19 beginning at 10 p.m., crews will begin working on the I-275 westbound bridge overpass over Three Mile Road in Campbell County. This work will require a single right lane closure on the ramp from I-471 southbound to I-275 westbound. One lane on the ramp will be maintained. This lane will pass the work zone on the right side and have its own dedicated lane to enter I-275 westbound. Additionally, a single right lane closure on I-275 westbound from the I-471 interchange to past the bridge overpass. Two left lanes will be maintained at all times.
These lane closures will remain in place 24/7 due to the extent of the work and to allow a safe area for the concrete to cure. The lanes are expected to reopen on late Saturday, Nov. 21.
Work on the I-275 westbound off-ramp to Licking Pike (KY 9) that was originally scheduled to begin on Thursday, Nov. 12 has been postponed due to expected inclement weather. This work will be rescheduled at a later date. KYTC will provide an update once this work has been scheduled.
GALLATIN AND CARROLL COUNTIES
I-71 – 52.77 – 57.36 mile points – A widening project aimed at reducing congestion and improving safety on I-71 in Carroll and Gallatin counties is in progress. The project will widen I-71 from its configuration of two lanes in each direction, to three lanes.
Final surface paving operations are complete in both directions of I-71. However, intermittent lane closures will still be necessary as crews complete remaining shoulder work and other miscellaneous project tasks.
Motorists should continue to use caution when traveling through the work zone, reduce speed and remain alert for lane closures, crews and equipment. All work is weather permitting.
Weather permitting, the overall project is expected to be completed Dec. 1, 2026. Learn more about the project here [Outside Link].
BOONE AND KENTON COUNTIES
Walton-Nicholson Road (KY 16) -- A maintenance project is expected to begin on Monday, Nov. 23. Crews will be performing milling/paving operations to patch various areas along the road:

- Boone County: from Dixie Highway (U.S. 25) (2.5 mile point) to the Boone/Kenton County line (2.37 mile point)
- Kenton County: from the Boone/Kenton County line (0.0 mile point) to Madison Pike (KY 17) (3.62 mile point)

This work will require various daytime single lane closures between the working hours of 7:30 a.m. and 3:30 p.m. Flaggers will be used to guide traffic safely through the work zone. Motorists are encouraged to find alternate routes to avoid delays.

No work will take place over the Thanksgiving holiday weekend from Thursday, Nov. 26 to Sunday, Nov. 29.

Weather permitting, this project is expected to be completed Friday, Dec. 4.
Campbell County
  • I-471 – 3.7 – 5.0 mile point – A bridge painting and cleaning project on the Memorial Parkway (KY 1120) bridge overpass over I-471 is now complete.

  • Alexandria Pike (U.S. 27) – 3.15 – 3.60 mile points – A highway safety improvement project at the intersection of U.S. 27 and Kenton Station Road (KY 1936) is in progress. The project will improve safety and traffic flow by converting the existing intersection to a Reduced Conflict U-Turn (RCUT).

    A traffic switch took place on Monday, Nov. 16, partially opening the Reduced Conflict U-Turn (RCUT) intersection while crews work toward transitioning traffic into its final configuration.

    Left turns from KY 1936 onto U.S. 27 are now prohibited. Motorists traveling from KY 1936 to U.S. 27 northbound must turn right onto U.S. 27 southbound, proceed to the designated U-turn lane and use the turnaround loon to access the northbound lanes.

    Concrete median work is complete; however, portions of the median remain blocked off with barrels to allow the concrete to cure. A single lane closure remains in place in each direction of U.S. 27 throughout the project limits. Remaining work includes the installation of final thermoplastic pavement markings, additional signage and miscellaneous project work. Rumble strip installation is complete.

    You can learn more about the project and how to navigate an RCUT by visiting the project webpage [Outside Link].

    Weather permitting, the overall project is expected to be completed by the end of November.

Gallatin County
  • I-71 – 56.64 – 59.94 mile points – A road rehabilitation project between Sparta Pike (KY 35) and northeast of the Boone Road (KY 465) overpass is in progress. Crews are performing pavement rehab, shoulder repairs and some guardrail work on various sections in the project area.
    The project is nearing completion, with only a few remaining items, including shoulder repairs, chip seal work and thermoplastic striping.

    While no lane closures are currently in place, intermittent daytime or overnight lane closures will be necessary to complete the remaining work. Motorists should continue to use caution when traveling through the work zone and be alert for lane closures, crews and equipment.

    Learn more about the project here [Outside Link]. Weather permitting, this project is expected to be completed by Dec. 1, 2026.
Kenton County
  • I-71/75 Southbound – 183.75 – 185 mile points – A concrete repair maintenance project is now complete.

  • Roebling Suspension Bridge – A sidewalk closure is in place as part of a maintenance project near the bridge. The sidewalk on the east side of the bridge will be blocked 24/7 until the project is completed. The sidewalk west of the bridge and all driving lanes will remain open. Weather permitting, the project is expected to be completed Tuesday, Nov. 20.

  • Locust Pike (KY 1930) – 3.88 – 4.53 mile points – A maintenance project on a portion of Locust Pike from Railroad Drive to Wilson Lane is in progress.

    The portion of road that was blocked to through traffic was reopened on Friday, Oct. 9. Crews continue working on brush clearing operations utilizing a temporary traffic signal on this corridor. Please drive carefully through the work zone.

    On Saturday, Nov. 21, crews will block Locust Pike/Whites Road at both access points with Decoursey Pike (KY 177) between the hours of 8 a.m. and 5 p.m. Crews will be installing two cross-culverts. Local traffic will be maintained. The road is expected to reopen by 5 p.m. to all traffic.

    Weather permitting, brush clearing operations are expected to be completed late November.