[KY 1947]

Error in Plans Results in Delay for the Opening of New Carter County Bridge

Posted: 30-Aug-2003 7:45PM CDT

An error in the plans for a new bridge over Barretts Creek in Carter County resulted in a bridge abutment being constructed at the wrong elevation. Work to correct the problem will delay the opening of the bridge a month or more to late September or early October.

More information: Ashland Daily Independent: Bridge opening delayed in Carter (Aug. 28, 2003) [Outside Link]

Comments

Updated: 30-Aug-2003 7:45PM CDT