District 3 Report: KY 884 Bridge Work Narrows I-165; Widening on the U.S. 31-W Bypass, KY 884 and U.S. 79; U.S. 68 Realignment
Kentucky Transportation Cabinet District 3’s traffic impact report for Nov. 15 through Nov. 20 lists these widening and new-alignment projects:
- KY 884, Bowling Green: widening to three lanes from McCoy Place to Fieldstone Boulevard, with a roundabout at Smallhouse Road, sidewalks on both sides and a new bridge over I-165 (William H. Natcher Parkway). New this week: work on that bridge closes one southbound lane of I-165 at mile point 0.5 during the day, Nov. 16 through Nov. 19.
- US 31 (U.S. 31-W Bypass), Bowling Green: widening to five lanes from KY 234 to Park Street, still expected to be completed in late 2027, with traffic narrowed to one lane in each direction plus a center turn lane through the construction zone.
- US 68, Green and Metcalfe counties: 1.2 miles of new alignment from near KY 729 in Green County to KY 745 in Metcalfe County, with 11-foot lanes, 4-foot paved shoulders, less curvature and grade, and a new bridge over Caney Fork Creek.
- US 79, Todd County: widening from the Tennessee state line to mile marker 3.
The safety project on U.S. 31-E in Barren County, which includes minor widening for a 4-foot buffer between opposing lanes, again expects overnight paving to begin this week. Elsewhere, KY 90 has reopened between Franklin Street and Morgan Street after its culvert replacement.
Earlier: District 3 Report: U.S. 68 Realignment and Widening on the U.S. 31-W Bypass, KY 884 and U.S. 79
The full report from Kentucky Transportation Cabinet District 3:
Kentucky Transportation Cabinet District 3 Traffic Impact Report for Nov. 15 Through Nov. 20
The District 3 area serves Allen, Barren, Butler, Edmonson, Logan, Metcalfe, Monroe, Simpson, Todd, and Warren Counties
BOWLING GREEN, Ky. (Nov. 15, 2026) – The expected traffic impacts in the Kentucky Transportation Cabinet District 3 area for Nov. 15 through Nov. 20 are listed below. All work is subject to change.
District 3 Report: U.S. 68 Realignment and Widening on the U.S. 31-W Bypass, KY 884 and U.S. 79
Kentucky Transportation Cabinet District 3’s traffic impact report for Oct. 30 through Nov. 6 lists these widening and new-alignment projects:
- US 68, Green and Metcalfe counties: 1.2 miles of new alignment from near KY 729 in Green County to KY 745 in Metcalfe County, with 11-foot lanes, 4-foot paved shoulders, less curvature and grade, and a new bridge over Caney Fork Creek.
- US 31 (U.S. 31-W Bypass), Bowling Green: widening to five lanes from KY 234 to Park Street, now expected to be completed in late 2027. Traffic is narrowed to one lane in each direction with a center turn lane through the construction zone.
- KY 884, Bowling Green: widening to three lanes from McCoy Place to Fieldstone Boulevard, with a roundabout at Smallhouse Road, sidewalks on both sides and a new bridge over I-165.
- US 79, Todd County: widening from the Tennessee state line to mile marker 3.
A safety project on U.S. 31-E in Barren County also includes minor widening, to create a 4-foot buffer between opposing lanes, and overnight paving was expected to begin that week.
The full report from Kentucky Transportation Cabinet District 3:
Kentucky Transportation Cabinet District 3 Traffic Impact Report for Oct. 30 Through Nov. 6
The District 3 area serves Allen, Barren, Butler, Edmonson, Logan, Metcalfe, Monroe, Simpson, Todd, and Warren Counties
BOWLING GREEN, Ky. (Oct. 30, 2026) – The expected traffic impacts in the Kentucky Transportation Cabinet District 3 area for Oct. 30 through Nov. 6 are listed below. All work is subject to change.
I-24 WB Ramps Closing on Monday in Christian County
From Kentucky Transportation Cabinet District 2:
CORRECTION: I-24 WB Ramps Closing on Monday in Christian County
Expected 2-3 week blockage
MADISONVILLE, Ky. (Oct. 22, 2026) – One of the ramps closing next week at the intersection of I-24 and U.S. 41A next week was incorrectly identified in the fist release. Crews will be closing the exit ramp from westbound I-24 to U.S. 41A and the cloverleaf entrance ramp from northbound U.S. 41A to westbound I-24 rather than the ramp from southbound U.S. 41A to I-24 westbound.
———————-
MADISONVILLE, Ky. (Oct. 22, 2026) – A contractor for the Kentucky Transportation Cabinet plans to block two ramps on westbound Interstate 24 beginning on Monday, Oct. 26 at 6 a.m.
At Exit 86, crews will block the exit ramp from I-24 westbound to U.S. 41A and the entrance ramp from U.S. 41A to westbound I-24 as the project to reconstruct I-24 from the 85.5-mile point to the Tennessee State Line (92 mm) continues.
Widening Continues on the U.S. 31-W Bypass, KY 884 and U.S. 79 in District 3
Three road widening projects are under way in Kentucky Transportation Cabinet District 3, according to its traffic impact report for Oct. 18–23:
- US 31 (U.S. 31-W Bypass), Bowling Green: widening to five lanes from KY 234 to Park Street in northern Bowling Green, expected to be completed in 2027. Through the construction zone, traffic is narrowed to one lane in each direction with a center turn lane.
- KY 884, Bowling Green: widening to three lanes from McCoy Place to Fieldstone Boulevard has started, with a roundabout at Smallhouse Road, sidewalks on both sides and a new bridge over I-165.
- US 79, Todd County: widening from the Tennessee state line to mile marker 3.
A safety project on U.S. 31-E in Barren County also includes minor widening, to create a 4-foot buffer between opposing lanes.
The full report from Kentucky Transportation Cabinet District 3:
Kentucky Transportation Cabinet District 3 Traffic Impact Report for Oct. 18 Through Oct. 23
The District 3 area serves Allen, Barren, Butler, Edmonson, Logan, Metcalfe, Monroe, Simpson, Todd, and Warren Counties
BOWLING GREEN, Ky. (Oct. 18, 2026) – The expected traffic impacts in the Kentucky Transportation Cabinet District 3 area for Oct. 18 through Oct. 23 are listed below. All work is subject to change.
Tennessee Schedules Public Meetings to Discuss I-75 Improvements
The Tennessee Department of Transportation will hold three public meetings this week to discuss possible improvements to I-75 from the Kentucky state line to the Georgia state line: Associated Press: TDOT public meetings this week about I-75 (Sept. 14, 2009) ![]()
I-65 Widening Project Underway
A project to widen I-65 from the Tennessee state line to Bowling Green is underway: Franklin Favorite: Highway project expected to take several months (June 15, 2006) ![]()
AP: Debate Grows over Impact of I-69 in Western Ky., Tenn.
Debate Continues over Faulty Guardrails in Tennessee
The president of a company accused of installing faulty guardrails on Tennessee road projects claims his company did nothing wrong: WPSD NewsChannel 6: Tennessee: Faulty Guardrail Debate (May 10, 2005) ![]()
I-75 Traffic Conditions Website
The Kentucky Transportation Cabinet has created a website with information about lane closures and construction on Interstate 75 near the Tennessee border: Kentucky Transportation Cabinet: I-75 Traffic Updates ![]()
I-75 in Northern Tennessee Reopens
After a week of delays, all lanes of I-75 in northern Tennessee have opened though work to repair a collapse of part of the interstate will continue for some time.
More information: WKYT: Interstate 75 reopened in Campbell County (March 11, 2005)
, Kentucky Transportation Cabinet: One lane of Interstate 75 southbound REOPEN to traffic in Tennessee (March 11, 2005)
, Associated Press: Work on slope expected to snarl I-75 traffic (Mar. 26, 2005) ![]()
Southbound I-75 in Northern Tennessee Expected to Remain Closed until Friday
The southbound lanes of I-75 in Tennessee between exits 160 and 134 are expected to remain closed until Friday, March 11. Weather has delayed the completion of cross over lanes that will allow southbound traffic to bypass a collapsed section of southbound lanes.
The Kentucky Transportation Cabinet has provided a list of several possible detours: Kentucky Transportation Cabinet: Interstate 75 southbound will remain closed until Friday, March 11 (March 8, 2005) ![]()
Portion of I-75 in Tennessee Closed
A portion of I-75 in Tennessee near the Kentucky state line has been closed due to a rock slide. It is unknown how long the closure will last: WKYT: Portion Of I-75 South Closed (March 1, 2005) ![]()
Wilkey Predicts I-65 Widening Project Could Begin This Spring
State Rep. Rob Wilkey believes that work to widen I-65 from the Tennessee state line to Bowling Green could begin this spring. He also has high hopes for a project to widen US 31W from KY 1008 south of Franklin to the Tennessee state line: Franklin Favorite: 'Road projects a go,' Rep. Wilkey says (Jan. 20, 2005) ![]()